Senior Center
Certification Site Visit Timeframe
|
Time
|
Activity
|
|
9:00 a.m.
|
Site team visit begins. After
introductions the team leader reviews the day’s agenda with the
director and the team, including schedule, for any volunteers
or others to meet with the team. *
|
| |
|
| |
The team meets alone
to compare finding from the preliminary reading of the SCOPE
tool and divide the SCOPE tool into sections for review. The
team will then meet with the director to ask questions.
|
| |
Tour of the facility (20
minutes or less, please) and satellites, if applicable. Arrangements
to visit satellites should be made before the site team arrives.
Visiting satellites may lengthen the site visit to more than
a day.
|
| |
|
|
9:45 a.m.
|
Review of documentation
materials begins. During this time, team members may need to
move around the center to conduct other site visit activities
as listed in the SCOPE tool.
|
| |
|
|
12:00 noon (or as convenient)
|
Lunch with center participants,
if possible. Site visitors will limit their participation to
one hour at most. Please inform Leslee Breen if site visitors
need to make some other arrangement for lunch (bring their own,
go out to eat, pay for the meal) so she can inform them.
|
| |
|
|
1:00 p.m.
|
Continue documentation
review
|
| |
|
| |
Meet with director,
or designated staff person, to ask questions or request information
as needed
|
| |
|
| |
Site team scores the
SCOPE tool and compiles a list of comments
|
| |
|
| |
Meet with the director
to advise him/her of findings and result of visit. Give the
director an opportunity to provide any additional comments or
information.
|
| |
|
|
4:30 p.m.
|
Site team leaves the
center if work is completed. If, by mid-afternoon, it is apparent
that the review will go past 4:30 p.m., the site visit team and
the center director will decide whether to work later or plan
for the site team to return the next morning.
|
| |
|
| |
* It is helpful for
the team to meet with a variety of people involved in the center,
but this must be balanced with other time demands of the team.
It is often convenient for such visits to occur informally during
lunch; but they also might be scheduled within a 20- to 30- minute
period during the morning. Please let Leslee Breen know immediately
if such interviews are scheduled.
|
WHAT THE SITE TEAM WILL NEED FROM THE CENTER
- A private, quiet
workspace with a table for reviewing documentation
- Adherence to the
schedule
- A guided tour of
the facility
- The director’s time
at the beginning and end of the day and periodically for questions
during the day
- Copies of documentation
materials arranged in a clear and orderly manner labeled to
indicate the question(s) they support. Please be very explicit
about why the documentation answers the question. Remember
that outsiders on the team do not know your community, so what
may be obvious to you may not be clear to them. Include only
enough documentation to answer the question.
- Freedom to move around
the center and talk to staff members, volunteers, participants
and others at the team’s discretion
- Lunch with participants,
if possible
- If applicable, in
advance of the team’s visit, please tell the center’s participants
to not wait around for the results of the visit, as there is
no guarantee about the time the team will finish.
|
WHAT THE
CENTER CAN EXPECT FROM THE SITE VISITORS
- Informality.
We will dress casually and come expecting to work and learn.
- Preparation. We
will have read and completed a preliminary scoring of all sections
for which material has been provided. We will have identified
any questions before arriving.
- Flexibility. We
will try to work around the center’s schedule and convenience
as much as possible. We will also be open to different ways
of achieving a given standard and documenting it. The team
is visiting to confirm the center’s self-assessment according
to the SCOPE standards; it is neither there as a monitor nor
an adversary.
- Confidentiality
and Disclosure. We will respect the confidentiality
of any personnel or client information we review.
|
Updated
October 17, 2006
|
|
List
of Senior Centers by County
Senior
Centers by Region 
Inquiry / Request
The
Ann Johnson Institute for Senior Center Management
NC
Senior Center Certification Process Brochure
Tools
for the Senior Center Certification Process (SCOPE)
Senior Center Capacity Survey
|